The short answer
A construction draw inspection is the site visit and report a lender relies on before it funds a draw. The inspector, usually an independent architect, engineer or construction consultant, compares the work in place with the contractor's payment request line by line against the schedule of values, checks stored materials and change orders, and reports whether the project is on plan, on schedule and in balance.
The inspection is one control among several. The OCC's Commercial Real Estate Lending handbook expects the amount of each draw to be commensurate with improvements made as of the inspection date, with lien waivers, a title update and a budget check before funds move. On HUD 221(d)(4) loans the process is set out in the MAP Guide, with a HUD-assigned inspector, monthly site visits and a 10% holdback that can step down after 50% and 75% completion when HUD's conditions are met.
Who performs a construction draw inspection?
On a bank loan, the lender chooses. The OCC handbook says banks typically require architect or engineering inspection reports with each draw, that a bank representative typically makes periodic site visits to confirm work is completed as reported, and that banks often retain an independent construction consulting firm when they lack in-house expertise. The handbook also wants construction credit administration independent of origination where possible.
Examiners test that independence. The handbook's internal control questions ask whether inspectors are competent and independent of the loan origination function, whether spot checks are made of their work, whether inspections run on an irregular schedule, and whether inspection requirements are written into the loan agreement and mortgage. On a HUD-insured advances loan the roles are fixed: HUD's construction analyst assigns a third-party inspector, the borrower's architect determines the amounts due by observing the work, and the HUD inspector checks the architect's numbers.
What does the draw inspector check?
The core comparison is percent complete. The contractor bills each line of the schedule of values at a percentage; the inspector sees what is actually installed. The OCC handbook says inspection reports typically state compliance with plans and specifications, support disbursements based on percentage complete, and say whether the project is progressing as anticipated. Build the line items once, at closing, with a schedule of values template, and every draw is checked against the same lines.
| Check | Compared against | Why the lender cares |
|---|---|---|
| Percent complete by line | Schedule of values and the contractor's payment application | Billing ahead of work leaves too little money to finish |
| Front loading | Early line items priced above their real cost | The OCC warns it almost certainly leaves insufficient funds to complete after a default |
| Plans and specifications | Approved drawings and specs | Noncompliant work is not collateral the lender should pay for |
| Schedule | Construction schedule and prior inspection | Delay drains the interest reserve and pushes completion |
| Stored materials | Invoices, quantities, storage location and insurance | Uninstalled materials can be lost, stolen or never used |
| Change orders | Approved change orders and the revised budget | Unapproved scope is unbudgeted cost |
| Funds to complete | Remaining loan, equity and contingency against remaining cost | The loan must stay in balance through completion |
How are stored materials inspected and paid?
Materials delivered but not installed are the riskiest dollars in a draw. The OCC handbook asks whether the loan agreement makes disbursement for deposits and materials not yet installed at the lender's discretion. On HUD loans the MAP Guide is specific: onsite stored materials must be itemized by quantity and cost with supporting invoices, and the HUD inspector spot checks the count, confirms the storage is acceptable and makes sure funds remain for transportation and installation.
Offsite storage is narrower still. The MAP Guide limits it to building components that are impractical to store on site, such as precast concrete panels, assembled bath or kitchen cores and fabricated structural steel, and excludes items such as kitchen appliances, carpeting and wood roof trusses. A request needs the architect's certification of a storage-site visit, a bill of sale, the security agreement, UCC filings, a counsel opinion on the lender's first lien and risk of loss insurance. Payment is limited to invoice value and is subject to a 10% holdback.
How does the inspection handle change orders?
A change order changes the budget the inspector measures against, so it has to be approved before it is paid. The OCC handbook says changes in construction plans should be reviewed by competent staff or a construction consulting firm and approved and documented by the bank and any take-out lender, and that a significant number of change orders can signal poor planning or construction problems. Its control questions ask whether change orders are approved in writing by the bank, the permanent lender, the architect, prime tenants with firm leases and the completion bonding company.
HUD goes further. Under the MAP Guide, additive change orders are not eligible on the contractor's monthly requisition and are referred to HUD for processing, and work done in anticipation of a future change order approval counts as noncompliant work. The inspector reports changes on each trip report, so the draw file shows the change order's approval date next to the first payment that relies on it.
What goes in a construction draw request?
The OCC handbook describes the draw request as setting out the funding request by construction phase and cost category, with the borrower's certification that loan conditions are met, that funds are used for the project and that suppliers and subcontractors have been paid. It should include waivers from subcontractors and suppliers for the work covered. Contractors commonly bill on the AIA G702 and G703 forms, which the MAP Guide accepts for releasing repair escrows on some 223(f) and 223(a)(7) loans. The cadence and the full package are covered in how the construction loan draw process works.
Two items sit outside the inspection but gate the funding. A mechanics lien waiver from each party paid on the prior draw shows the money reached the trades. A title update, which the OCC control questions describe as a date-down endorsement with each draw where applicable, confirms no lien has been recorded ahead of the new advance. ALTA publishes construction loan endorsements in its 32 series and a disbursement endorsement, ALTA 33-06.
How much retainage do lenders hold back?
Under a progress payment plan, the OCC handbook says the bank normally holds back 10 to 20 percent of each payment to cover cost overruns or unpaid bills, and releases it with the final draw. HUD's MAP Guide sets a schedule for 221(d)(4) and other insured advances loans. Retainage starts at 10% of the contractor's monthly payments for acceptably completed work and acceptably stored materials, and can step down if the contractor has no identity of interest above a 5% equity interest in the owner, the surety consents in writing and HUD has no concerns about the contractor's performance.
| Project completion | Retainage held | Condition |
|---|---|---|
| Up to 50% | 10% | Standard holdback from each advance |
| 50% to 75% | May reduce to 5% | Reduction rider, surety consent, no performance questions, Regional Production Director decision |
| 75% to final endorsement | May reduce to 2.5% | Same conditions |
| After 90% contract completion | Partial early release possible | Regional Production Director approval on a joint request |
| Next to final advance | Balance may be released | Cost certification reviewed, approvals and certificates of occupancy issued, Permission to Occupy for all units, survey submitted, holdback kept for items of delayed completion at 150% of HUD's estimate |
How does the HUD 221(d)(4) draw process work?
Each advance on an insured advances loan runs on form HUD-92403, Application for Insurance of Advance of Mortgage Proceeds, which the borrower initiates, with the contractor's requisition on form HUD-92448. The MAP Guide splits approval by stage: the initial and final advances go to HUD for review and approval, while interim advances are approved by the MAP lender based on the HUD inspector's approval of the construction amount. The lender's construction loan administrator signs both forms in the HUD signature blocks for interim draws, and with the final advance the lender submits form HUD-92451, the financial record of payments made during construction.
The HUD inspector visits the site once a month for new construction and substantial rehabilitation, records each visit on a trip report (form HUD-95379), and can reduce the contractor's request on the requisition, explaining why in the trip report. Before advancing, the lender must ensure clear title and notify HUD in writing when mechanics liens stay unresolved for more than 60 days. The Guide also treats the interest allocation as overspent when the share used runs 10% or more ahead of the completion shown on the progress schedule. The FHA multifamily loans post covers the program around it.
What does construction loan monitoring cover between draws?
The inspection is a monthly snapshot. Monitoring is the running picture. The OCC handbook describes monthly reports of work completed, costs to date, costs to complete, construction deadlines and loan funds remaining, plus periodic review of the developer's financial statements, updated credit reports and confirmation that property taxes are paid. It also says overruns caused by poor projections or management would ordinarily be covered by the borrower, not by drawing down the contingency.
When a change order or overrun moves the budget, rerun leverage on the new total with a loan-to-cost calculator before the next draw funds. A loan that has fallen out of balance needs equity in before more loan money goes out. Teams that run construction loan management as a monthly routine catch that at the draw, not at the final advance.
What happens when the inspector disagrees with the draw?
The lender funds what the inspection supports, not what was requested. The OCC control questions ask whether the loan agreement lets the bank withhold disbursements if work is not done to the approved specifications, and whether disbursements are made only after reviewing written inspection reports and checked against previous disbursements. On HUD loans the inspector enters trade item modifications on the requisition and the lender approves the reduced amount.
The cleanest files record each finding as an open item with an owner: the line reduced, the reason, and what the contractor must show to bill it next month. Teams choosing between a workbook and a shared checklist for that list can compare the approaches in Prodeal vs Smartsheet. The inspection requirements themselves belong in the loan documents from day one, which the construction loan closing checklist covers.
What does the final draw inspection confirm?
Before releasing the final draw and the holdback, the OCC handbook lists confirming that all lien waivers or releases are in from contractors, subcontractors and suppliers, reviewing the final inspection report to confirm the project is complete and meets building specifications, and confirming the certificate of occupancy. Its control questions add sworn and notarized releases of mechanics liens before final disbursement.
On a bridge loan with future funding the same logic applies at smaller scale: each renovation draw is inspected, and the last one closes out the capex budget. The companion post on multifamily bridge loans covers how those draws fit the loan's business plan and exit.
Questions lenders ask
- What is a construction draw inspection?
- A site visit and written report confirming the work billed in a draw request is in place and meets the plans. The lender uses it to decide how much of the draw to fund.
- Who pays for a HUD draw inspection?
- On a bank loan, the loan agreement decides. On HUD loans the MAP Guide sets a HUD inspection fee of $5 per thousand of the mortgage amount for new construction, or $5 per thousand of total improvement costs for substantial rehabilitation, and treats HUD inspection fees as allowable costs at cost certification.
- How often are draw inspections done?
- Usually once per draw: the OCC handbook says banks typically require architect or engineering inspection reports with each draw. On HUD new construction and substantial rehabilitation, the MAP Guide calls for one HUD inspector site visit each month.
- What is the difference between retainage and a holdback?
- The terms overlap. Retainage is withheld from the contractor's payments under the construction contract; holdback is the lender's term for the portion of each advance it keeps back. On HUD loans the MAP Guide uses both for the same 10% amount.
- Can a lender fund stored materials?
- Yes, at its discretion and with evidence: invoices, quantities, secure storage, insurance and waivers. HUD allows offsite storage only for eligible building components, with extra lien and insurance documentation.
- What forms are used for HUD construction draws?
- Form HUD-92403 for the advance, HUD-92448 for the contractor's requisition, HUD-95379 for the inspector's trip report, and HUD-92451 for the lender's record of disbursements.
- What does the inspector do if work is billed ahead of progress?
- Reduces the line to the percent actually complete and reports why. The lender funds the reduced amount, and the contractor bills the balance once the work is in place.
- Does the title policy need updating with each draw?
- The OCC handbook says the lender's title policy should be updated with each draw so the title company can confirm no liens are outstanding, which matters most where mechanics liens can take priority over the bank's lien.
Sources and further reading
- OCC, Comptroller's Handbook, Commercial Real Estate Lending, Version 2.0 (March 2022, reputation risk references removed March 2025): ADC credit administration, disbursement processes and internal control questions, read 2026-11-06
- HUD, Multifamily Accelerated Processing (MAP) Guide 4430.G, March 2021 revision, Chapters 3 (3.1.9), 12 (12.7, 12.15.5, 12.17) and 13 (13.14.7), and Appendix 12, read 2026-11-06
- ALTA, policy forms list including Endorsement 32 series Construction Loan and 33-06 Disbursement, read 2026-11-06

Ian Group has served as Head of Customer Success at Prodeal since March 2018. He leads customer onboarding, training and platform adoption for lenders and commercial real estate firms, while contributing to the company's product strategy and roadmap. Before joining Prodeal, he practiced commercial real estate law in New York. He holds a JD from Albany Law School.
- The construction loan closing checklistWhere inspection requirements get written in.
- How does the construction loan draw process work?The monthly cadence around the inspection.
- Schedule of values templateThe line items every inspection measures.
- Construction draw, definedThe mechanics in one paragraph.
- HUD 221(d)(4), definedThe insured advances program.
- Multifamily bridge loans: structure, exits and lender diligenceFuture funding draws on transitional loans.